ROAD PROGRAM UPDATE–July 8, 2022 RECONSTRUCTION OF MARSHALL AVENUE UNDERWAY


We are pleased to announce that the reconstruction of Marshall Avenue between Covert Avenue and Orchid Street has begun. As previously announced this is a total reconstruction which includes new curbing, drainage gutters, driveway aprons, drainage basins and a new asphalt roadway.

Weather permitting we expect the roadway to be completed in mid-August. Trees cannot be planted in August but we will plant new larger caliper trees where possible in late September early October during planting season.

If you have any questions please contact the Department of Public Works at 516-326-6320.