Roadway and Drainage Improvements

Starting August 3, United Paving Corp. will be performing road improvements under The Village of Floral Park 2020 Roadway and Drainage Improvements Program.

As part of the improvements, we will be performing roadway and underground drainage work in the areas as follows:

Emerson Avenue and Lowell Avenue (Area A)
Mobilization and drainage work:  August 3 – August 21
Road paving work:  September 28 – October 9

West Hitchcock Avenue & Depan Avenue (Area B)
Mobilization and drainage work:  August 17 – September 4
Road paving work:  September 28 – October 9

Crocus Avenue from Elm Avenue to Maple Avenue (Area C)
Mobilization and drainage work:  August 31 – September 25
Road paving work:  September 28 – October 9

During these time periods, you will have limited access to your driveway and/or roadway.  Schedule is subject to change due to inclement weather and unforeseen conditions, please check the village website FPVillage.org for any updates.

Every effort will be made to inconvenience you as little as possible.  Restoration of lawns disturbed by construction operations will be performed as soon as practical.

Your cooperation during the period of construction will be appreciated.

If you have any questions regarding the contract work, please contact the Village of Floral Park at 516-326-6320 or [email protected]

Very Truly Yours,
Kevin Ginnane
Superintendent of Public Works