3TC Work Near Tunnel Street

3TC advises the Village that there will be work performed on the Hempstead line in the area of Tunnel Street on Saturday, January 30th during the daytime.


************************************************************************

Atlantic Avenue Road Closure Schedule Updates from LIRR

The Village has been informed of a schedule change for the Atlantic Avenue Road Closure as follows:

The Long Island Rail Road will be performing construction work relative to the third track construction starting on February 1, 2021 for approximately 3-4 weeks.  Work will occur on the north side of Atlantic Avenue, between Carnation and Childs Avenue.  The scope of work includes the installation of a new retaining wall, service steps and a signal shed at track level.  Once completed, the fencing and shrubbery will be restored. 

Methods of construction will include drilling for piles, therefore a road closure in this area will be necessary to accommodate the large equipment.  The duration for road closure is approximately 3 weeks, from Monday, February 1 – Friday, February 19, 7:00 am – 3:30 pm each week day.   During this time all traffic on Atlantic Avenue between Carnation and Childs Avenue will be restricted to emergency vehicles and for necessary access to driveways encompassed in this area.  The LIRR will be providing traffic control signage and a flagger to accommodate the detours.  All schedules are weather dependent, changes will be communicated as received.

Click here for detour map.

If you have any questions, please call the Department of Public Works at 516-326-6320.

***********************************************************************

WEEKEND LIRR & 3TC WORK

3TC WORK NEAR TUNNEL STREET

3TC advises the Village that they will not be performing any nighttime work or work on Sunday, but there will be work performed in the area of Tunnel Street on Saturday during the daytime. 3TC states that all access for this work on Saturday will be from the LIRR right-of-way and it will not require 3TC to have their vehicles or equipment on Tunnel Street.

POSSIBLE LIRR NIGHTTIME WORK THIS WEEKEND ON MAINLINE (SATURDAY NIGHT into SUNDAY MORNING)

The Village has been informed by the LIRR that there will be overnight work taking place between Queens Village and Mineola on the Mainline between 5:00 pm on Saturday evening and 5:00 am on Sunday morning. However, the LIRR was unable to confirm whether any of this overnight work will be taking place along the LIRR tracks within the Village of Floral Park.

***********************************************************************
Third Track Update January 14, 2021: Road Closures on Atlantic Avenue Between Carnation and Childs Avenues

The Long Island Rail Road will be performing construction work relative to the third track construction starting on Monday, January 25, 2021 for approximately 3 weeks.  Work will occur on the north side of Atlantic Avenue, between Carnation and Childs Avenue.  The scope of work includes the installation of a new retaining wall, service steps and a signal shed at track level.  Once completed, the fencing and shrubbery will be restored. 

Methods of construction will include drilling for piles, therefore a road closure in this area will be necessary to accommodate the large equipment.  The duration for road closure is approximately 2 weeks, from Monday January 25 – February 5, 7:00 am – 3:30 pm daily.   During this time all traffic on Atlantic Avenue between Carnation and Childs Avenue will be restricted to emergency vehicles and for necessary access to driveways encompassed in this area.  The LIRR will be providing traffic control signage and a flagger to accommodate the detours.  All schedules are weather dependent, changes will be communicated as received.

Click here for detour map.

If you have any questions, please call the Department of Public Works at 516-326-6320.

************************************************************************
Third Track Update January 14, 2021: Switch Work by Tunnel Street

As a part of the replacement of the track “switches” on the LIRR Hempstead Line in relation to the Third Track Project, 3TC has begun work on the Hempstead Line east and west of Tunnel Street.

     The tunnel between Magnolia Avenue and Tunnel Street will remain open for pedestrians during this work, but construction activity will be taking place in close proximity to the tunnel. 3TC will have flagmen present and may intermittently close off the tunnel with “caution tape” for short durations for safety reasons when equipment is in use near the exit on the Tunnel Street side of the tunnel. Please also exercise caution when using the tunnel and be aware of equipment that may be in use in the vicinity.

    If you have any questions, please call the Department of Public Works at 516-326-6320.