Water Authority Work Tentatively Scheduled to Begin Monday, May 20, 2024

The Water Authority of Western Nassau County (WAWNC) has notified the Village that the anticipated start date for their water main replacement project is May 20, 2024. See Water Main Replacement Notice. This planned work will take place on the blocks south of Tulip Avenue between Raff Avenue and Floral Parkway. See attached map.

Many of the roadways on these same blocks were previously dug up by National Grid as part of gas main replacement work. Once this work by WAWNC is complete, the Village will be able to undertake a curb-to-curb repaving of these blocks. By coordinating the Village’s Road Repaving Program with National Grid and WAWNC, the Village will be able to offset a majority of the repaving costs due to the funds received from National Grid and WAWNC.